Articles · November 2026

When does your project need an independent technical report?

By Eng. Salah Salem Al-Bakri — Accredited Arbitrator at the Qatar International Center for Conciliation and Arbitration (QICCA), and Ministry of Justice accredited engineering and real-estate expert

اقرأ المقال بالعربية

In many projects, a dispute does not begin with a major disagreement. It begins with a small comment on workmanship, a delayed payment, or a different reading of a contract clause. Over time each party holds firmly to its own account, and a technical question turns into a dispute that is hard to resolve. It is precisely at this stage that an impartial technical opinion becomes a tool for protecting the project, not just an additional step.

What is an independent technical expert report?

It is a report prepared by a specialist expert who has no interest in any of the project parties. The expert examines the technical facts, compares them with the contract, drawings, specifications and correspondence, and reaches reasoned conclusions that can be relied upon in negotiation or settlement, or submitted to arbitral tribunals and courts.

Six situations that call for an independent report

1. Project delay and shifting responsibility

When handover is late and the contractor attributes it to delayed approvals or variations, while the owner attributes it to poor performance, both parties need a time-based analysis that identifies the actual causes of delay, each party’s share of them, and their effect on the completion date.

2. Disputes over quality or compliance with specifications

Defects in construction, finishes, or electrical and mechanical systems call for a technical inspection that documents the defect, identifies its cause, and assesses whether it results from a design, construction or operational fault, together with an estimate of the remedial cost.

3. Disputes over quantities, payment certificates and additional works

Many financial disputes stem from differences in measuring executed quantities, or in classifying a piece of work as within the contract scope or as a variation entitled to payment. An independent report settles these points with figures and documents.

4. Termination of the contract or removal of works

Before or immediately after termination, the actual percentage of completion, the condition of the site and the materials supplied must be documented. This protects both parties and prevents evidence from being lost if the work passes to another contractor. This type of report is known as a condition (status) report.

5. Before handover, purchase or financing

Before taking over a building, buying it, or offering it as security for financing, a technical report reveals its true condition, its remaining structural life and the works it requires, so that the decision rests on accurate information rather than impressions.

6. Before resorting to arbitration or litigation

An independent report helps assess the strength of the technical position before filing a claim. It may open the door to settlement and save considerable time and cost. If the dispute continues, the technical file is ready and organised from the outset.

What should the report contain?

Conclusion

The earlier a technical report is commissioned, the greater its value: the evidence on site is still there, and the options open to the parties are still available. Investing in an impartial technical opinion at the right time costs far less than a prolonged dispute.

This article is for general awareness and does not constitute technical or legal advice on any particular case.

Does your project need an independent technical report?

Contact us to discuss your case.

Request a service Contact us on WhatsApp

Eng. Salah Salem Al-Bakri · Doha, Qatar